Status of
"STUDY" mode Transmission Service Requests:
(
40
pending)
- Request #1285207, ACTIVE
-- Rollover, Determination of ATC pending, Status pending
- Request #952950 , ACTIVE
-- Consolidation request, Status pending
- Request #854324 , ACTIVE
-- SIS Pending (WEST SIDE)
- Request #825675 , ACTIVE
-- SIS In-progress (jointly with MISO), FS Pending
- Request #824726 , ACTIVE
-- SIS In-progress (jointly with MISO), FS Pending
- Request #796103 , ACTIVE
-- SIS Pending (Reduced to 31.5 MW)
- Request #781046 , ACTIVE
-- Consolidation request, Status pending
- Request #736108 , ACTIVE
-- SIS In-progress
- Request #607390 , ACTIVE
-- SIS Completed, MAPP DRS Approval, FS
Completed, Status pending.
Abbreviations:
SIS =
System Impact Study, FS =
Facilities Study
CA = Construction Agreement, SA = Service Agreement
Historical
Summary of RECENT changes:
Since prior xx/xx/xx Posting (where xx Requests
were pending):
1. New Requests (xx):
2. Processed Requests (xx):