Functional Separation: DSW 100% complete on functional separation. Standards of Conduct training was conducted during the Summer of 2004.

Physical Separation: DSW 50% complete on physical separation. Modular system furniture delivery and construction will delay completion until April 30, 1999. In the interim:

On January 15, 1999, generation/resource scheduling was separated from transmission scheduling and moved to temporary offices in conference room.

Resource Manager moved out of Operations to new office in Power Marketing on January 20, 1999.

Computer Separation: DSW 100% complete on computer separation requirements.

OASIS Operational: DSW OASIS node 100% operational. Standards of Conduct, organization charts, and job descriptions posted on OASIS. Monthly progress report will also be posted until physical separation is complete. Postings for several bi-directional transmission paths have been made.