Sierra Pacific Power Company OASIS


Sierra Pacific Policy on Transmission Reliability Margin and Capacity Benefit Margin

Effective Date: 09/24/2007

 Date last Re-evaluated:  09/24/2007

Definitions

According to the Western Electricity Coordinating Council (WECC) document, Determination of Available Transfer Capability within the Western Interconnection, the definitions for Transmission Reliability Margin (TRM) and Capacity Benefit Margin (CBM) are: 

TRM

“TRM is the amount of transmission transfer capability necessary to provide a reasonable level of assurance that the interconnected transmission network will be secure under a broad range of uncertainties in system conditions. TRM accounts for the inherent uncertainty in system conditions and system modeling, and the need for operating flexibility to ensure reliable system operation as system conditions change.”

 Further, the Document specifically addresses possible TRM components. They are: 

  1. Transmission necessary for the activation of operating reserves
  2. Unplanned transmission outages (for paths in which contingencies have not already been considered in establishing the path rating)
  3. Simultaneous limitations associated with operation under a nomogram
  4. Loading variations due to balancing of generation and load
  5. Uncertainty in load distribution and/or load forecast
  6. Allowances for unscheduled flow

CBM

“CBM is the amount of firm transmission transfer capability reserved by Load Serving Entities (LSEs) on the host transmission system where their load and generation resources are located, to enable access to generation from interconnected systems to meet generation reliability requirements. CBM is a uni-directional quantity with identifiable beneficiaries, and its use is intended only for the time of emergency generation deficiencies.”

 

Sierra Policy---TRM

Sierra Pacific Power Company (Sierra) utilizes TRM. Sierra specifically utilizes items #1 through #5 above. Sierra’s transmission system is quite constrained (dynamically and post-disturbance voltage deviations) from various single contingencies. The import/export operating nomograms, addressing item #3 above, posted on the Internet at OATiOasis/Transmission Information/Import Nomograms, fully describe the system-wide import limit factoring in the “simultaneous limitations associated with operation under a nomogram.”

The true system simultaneous import limit, determined by study, is 1010 MW. Sierra also applies additional TRM to account for minor load variations (item #4) and small errors in load forecast (item #5). The total TRM for those items is 10 MW. In application, the total import capability described in the operating nomograms is decremented by nomogram component. 

In essence, the difference between the non-simultaneous Sierra import limit (i.e., the arithmetic sum of all paths Total Transfer Capability (TTC)---1357 MW), the simultaneous limit (i.e., the simultaneous interaction of all the paths---1010 MW), and the minor load variations (10 MW) is the total system TRM. The TRM formula is:

 

Non-Simultaneous Import Limit (i.e., sum of all path ratings)

1399 MW

less

 

Operation under a nomogram

1010 MW

TRM, part A

389 MW

Plus

 

Loading Variations and Uncertainty in Load Distribution

10 MW

Total TRM

399 MW

 

 

 

In order to manage Available Transmission Capacity (ATC) calculations, Sierra has chosen to create a “virtual path” (to reflect the import limit) in series with the physical paths. Rather than posting to TRM individual paths, on OATi OASIS, the “virtual path” has a TTC of 1399 MW and a TRM of 399 MW posted.  The difference (1000 MW) is equal to the import limit allowable for scheduling.

When customers attempt to reserve transmission capability to serve load within the SPPC system, the ATC on both the physical path under consideration and the series virtual path are decremented.  Schedules on all physical paths must cross the virtual path to reach the load.

Previously, the 1000 MW import limit was programmed as the TTC value for the "import" virtual path. As of today, 9/17/2007 the "import" path TTC is 1399 MW and the TRM value is 399 MW. Net resulting ATC calculations yield the same results as before.

 

TRM for Reserve Sharing

Sierra is a member of the Northwest Power Pool (NWPP) Reserve Sharing Group.  The NWPP exists to allow member control areas/balancing areas to reduce the contingency reserves they may carry and allow access to other reserves to meet the requirements of the NERC Disturbance Control Standard (DCS) detailed in BAL-002-0.

The Sierra TRM for contingency reserves is variable since it is load based.  According to the WECC Minimum Operating Reliability Criteria (MORC), contingency reserves are seven percent of the Load Responsibility.  Load Responsibility is the actual control area/balancing area demand less firm imports plus firm exports.  For purposes of defining TRM for reserves, Sierra has neglected firm exports.  Further, all imports are deemed firm to simplify the calculations.  Thus, the contingency reserve requirement becomes: (Load – import)*0.07.

To meet DCS, all control areas/balancing areas must have access to reserves equal to at least their Most Severe Single Contingency (MSSC); the largest generator output.  For Sierra, the generator output is always greater than the internal contingency reserves. The remainder must be accessible, from the NWPP entities, on the Midpoint/Humboldt intertie (the only path available using the NWPP automated reserve sharing system).

Since load varies, the NWPP contingency reserves needed by SPPC vary as well.  While the load changes moment-to-moment, Sierra chose to set aside TRM (on the Midpoint/Humboldt intertie only) based upon the peak load expected in a calendar quarter.  TRM is thus:

TRM = MSSC – (Maximum Quarterly Load – Expected Import)*.07

 

The Transmission Provider will assess the TTC and the ATC of the Transmission System to provide the service requested as prescribed by FERC regulations and in accordance with the process detailed in Sections 4 and 5 of the Transmission Provider's annual FERC Form 715 submittal.  In determining the level of capacity available for new transmission service requests, the Transmission Provider will take into consideration that capacity needed to meet current and reasonably forecasted loads of Native Load Customers, existing Network Customers, existing Firm Point-To-Point Transmission Service Transmission Customers, pending applications for Firm Point-To-Point Transmission Service, and other existing contracts.

 

Sierra Policy---CBM

Sierra Pacific Power Company does not use CBM.

 

Re-evaluation

Sierra Pacific Power Company will re-evaluate TRM needs annually.   Currently Sierra Pacific Power Company does not use CBM, and will re-evaluate CBM as it is requested by Transmission Customers as well as CBM will be re-evaluated at a minimum annually.

 

 

 

Contact
Jay Campbell
775-834-3782
mailto:jcampbell@sppc.com?subject=Help on CBM