Descriptions of the Transmission Paths Available for
Reservation
Summary
This document is
meant to summarize Sierra paths for reservation and their Total Transfer
Capability (TTC). This document also describes Sierra's import capability
and how it is managed within the OATi Available Transmission Capability
(ATC) calculation methodology.
A
system map, under Transmission Information, showing all the available
paths is also available.
An outage, whether forced or scheduled, can
change a path or import limit at any time. Please check the
Outage report for and changes.
If no outages are listed, customers can assume
that all path ratings and import limit are as described in this document.
The path ratings described here are all firm
capabilities. All real-time and day-ahead non-firm ATC is based upon
schedules and counter-schedules. Non-firm ATC beyond day-ahead is equal to
the firm capability.
Path Ratings
Following is a list of the ratings for all of Sierra's path segment:
|
POR |
POD |
Segment Name |
Segment TTC |
|
HILLTOP345 |
SPPC1 |
BPAT to Sierra |
300 |
|
SUMMIT120 |
SPPC1 |
CAISO/PG&E to Sierra |
100 |
|
SILVERPEAK55 |
SPPC1 |
CAISO/SCE to Sierra |
17 |
|
SPPC |
SPPC1 |
Export Limit |
500 |
|
M345 |
SPPC1 |
Idaho Power to Sierra |
500 |
|
SPPC1 |
SPPC |
Import Limit |
1000 |
|
GON.IPP |
EAST |
LADWP/IPP to Sierra |
200 |
|
GON.PAV |
EAST |
PacifiCorp East to Sierra |
370 |
|
SPPC1 |
EAST |
Path 32 Export |
235 |
|
EAST |
SPPC1 |
Path 32 Import |
370 |
|
SPPC1 |
HILLTOP345 |
Sierra to BPAT |
300 |
|
SPPC1 |
SUMMIT120 |
Sierra to CAISO/PG&E |
105 |
|
SPPC1 |
SILVERPEAK55 |
Sierra to CAISO/SCE |
17 |
|
SPPC1 |
M345 |
Sierra to Idaho Power |
262 |
|
EAST |
GON.IPP |
Sierra to LADWP/IPP |
200 |
|
EAST |
GON.PAV |
Sierra to PacifiCorp East |
235 |
|
SPPC |
SPPC |
Sierra to Sierra |
|
Path Index
Import Limit
From Bonneville Power Administration...
From Idaho Power Company...
From Pacific Gas & Electric Company (PG&E)...
From PacifiCorp's Utah Division...
From Los Angeles Department of Water and Power (LADWP)
and the Intermountain Power Project...
From Southern California Edison (SCE)...
Import Limit
The import limit for Sierra Pacific defines the simultaneous
interaction between a path and all Sierra's other paths. It defines
the safe operating region factoring in the single largest
contingency and the requirements listed in the "WECC Planning and
Operating Standards." The import nomogram is found at
http://www.oatioasis.com/SPPC/SPPCdocs/Import_Nomograms_Scheduling_Summer_2004.xls.
The curves are for all lines in-service.
If an outage occurs that can effect the import limit, forced or
scheduled, the details and its effect are posted at
http://www.oatioasis.com/SPPC/SPPCdocs/outage.html. Those
postings will have any new import limit required by the outage.
Any time the total system import is below 700 MW, the tie flows are
such that the import nomograms are not needed. Above 700 MW,
Sierra's pre-schedule and real-time scheduling staff will examine
all schedules to ensure they are within the import nomograms. Sierra
will utilize the "WECC Minimum Operating Reliability Criteria"
(MORC) rules for phase shifter operation to balance the import
capability. Essentially, the MORC gives phase shifter operators
great leeway in establishing actual power flows such that the
Alturas and PG&E ties can be controlled to optimize import
capability..
Sierra can adjust the Alturas and PG&E phase shifters between zero
MW actual path flow and 20 MW beyond (40 MW for Alturas) the path
schedules. Those schedules are listed on the
Intertie and Netloading page.
From Bonneville Power Administration to:
- Sierra Pacific Network:
A TTC of 300MW is provided from Sierra's
interconnection with BPA (at Hilltop substation) to the Sierra
Pacific Network. Available transmission capacity for this path is posted
on the OASIS under the path name HILLTOP345 / SPPC.
Idaho Power Company:
A (TTC) of 262MW is provided from Sierra's
interconnection with BPA (at Hilltop substation) to Sierra's
interconnection with Idaho Power Company (at Midpoint
substation). Available transmission capacity for this path is posted
on the OASIS under the path name HILLTOP345 / M345.
Pacific Gas & Electric Company (PG& E):
A TTC of 105MW provided from Sierra's
interconnection with BPA, at the Hilltop substation, to Sierra's
interconnection with PG&E at the Donner Summit Metering Station.
Available transmission capacity for this path is posted on the
OASIS under the path name
HILLTOP345 / SUMMIT120..
PacifiCorp's Utah Division:
A TTC of 235MW provided from Sierra's
interconnection with BPA at the Hilltop substation to Sierra's
interconnection with the PacifiCorp's Utah division on the
Gonder-Pavant transmission line. Available transmission capacity
for this path is posted on the OASIS under the path name
HILLTOP345 /
GON.PAV.
Los Angeles Department of Water and Power (LADWP) and the Intermountain Power Project:
A TTC of 200MW provided from Sierra's
interconnection with BPA at the Hilltop substation to Sierra's
interconnection with LADWP and other Intermountain Power Project
Parties on the Gonder-IPP transmission line. Available transmission
capacity for this path is posted on the OASIS under the path name
HILLTOP345 /
GON.IPP.
Southern California Edison (SCE):
A TTC of 17MW provided from Sierra's
interconnection with BPA at the Hilltop substation to Sierra's
interconnection with the SCE a the Control substation. Available
transmission capacity for this path is posted on the OASIS under the
path name
HILLTOP345 /
SILVERPEAK55..
top
From Idaho Power Company to:
-
Sierra Pacific Network:
A TTC of 500MW is provided from Sierra's
interconnection with
Idaho Power Company at Midpoint substation to the Sierra Pacific
Network. Available transmission capacity for this path is posted
on the OASIS under the path name M345 / SPPC.
-
Bonneville Power Administration:
A TTC of 300MW is provided from Sierra's
interconnection with Idaho Power Company at the Midpoint substation
to Sierra's interconnection with Bonneville Power Administration at
the Hilltop substation. Available transmission capacity for this
path is posted on the OASIS under the path name M345 / HILLTOP345.
-
Pacific Gas & Electric Company (PG&E):
A TTC of 105MW is provided from Sierra's
interconnection with the Idaho Power Company at the Midpoint
substation to Sierra's interconnection with PG&E at the Donner
Summit Metering Station. Available transmission capacity for this
path is posted on the OASIS under the path name M345 / SUMMIT120.
PacifiCorp's Utah Division:
A TTC of 235MW is provided from Sierra's
interconnection with the Idaho Power Company at the Midpoint
substation to Sierra's interconnection with PacifiCorp's Utah
division on the Gonder-Pavant transmission line. Available
transmission capacity for this path is posted on the OASIS under the
path name M345 / GON.PAV.
Los Angeles Department of Water and Power (LADWP) and the
Intermountain Power Project:
A TTC of 200MW is provided from Sierra's
interconnection with the Idaho Power Company at the Midpoint
substation to Sierra's interconnection with LADWP and other
Intermountain Power Project Parties on the Gonder-IPP transmission
line. Available transmission capacity for this path is posted on the
OASIS under the path name M345 / GON.IPP.
Southern California Edison (SCE):
A TTC of 17MW is provided from Sierra's
interconnection with the Idaho Power Company at the Midpoint
substation to Sierra's interconnection with SCE at the Control
substation. Available transmission capacity for this path is posted
on the OASIS under the path name M345 / SILVERPEAK55.
top
From Pacific Gas & Electric Company to:
-
Sierra Pacific Network:
A TTC of 100MW is provided from Sierra's
interconnection with
PG&E at Summit metering point
to the Sierra Pacific Network. Available transmission capacity
for this path is posted on the OASIS under the path name
SUMMIT120 / SPPC.
Bonneville Power Administration:
A TTC of 100MW is provided from Sierra's
interconnection with PG&E at the Donner Summit Metering Station to
Sierra's interconnection with Bonneville Power Administration at the
Hilltop substation. Available transmission capacity for this path is
posted on the OASIS under the path name SUMMIT120 / HILLTOP345.
Idaho Power Company:
A TTC of 100MW is provided from Sierra's
interconnection with PG&E at the Donner Summit Metering Station
to Sierra's interconnection with the Idaho Power Company at
the Midpoint substation. Available transmission capacity for
this path is posted on the OASIS under the path name SUMMIT120
/ M345.
PacifiCorp's Utah Division:
A TTC of 100MW is provided from Sierra's
interconnection with PG&E at the Donner Summit Metering Station
to Sierra's interconnection with PacifiCorp's Utah Division on the
Gonder-Pavant transmission line. Available transmission capacity
for this path is posted on the OASIS under the path name
SUMMIT120 / GON.PAV.
Los Angeles Department of Water and Power (LADWP) and the
Intermountain Power Project:
A TTC of 100MW is provided from Sierra's
interconnection with PG&E at the Donner Summit Metering Station
to Sierra's interconnection with LADWP and other Intermountain Power
Project Parties on the Gonder-IPP transmission line. Available
transmission capacity for this path is posted on the OASIS
under the path name
SUMMIT120 / GON.IPP.
Southern California Edison (SCE):
A TTC of 17MW is provided from Sierra's
interconnection with PG&E at the Donner Summit Metering Station
to Sierra's interconnection with SCE at the Control substation.
Available transmission capacity for this path is posted on the OASIS
under the path name
SUMMIT120 / SILVERPEAK55.
top
From PacifiCorp's Utah Division to:
-
Sierra Pacific Network:
A TTC of 370MW is provided from Sierra's
interconnection with
PacifiCorp's Utah division on the Gonder-Pavant line to the
Sierra Pacific Network. Available transmission capacity for
this path is posted on the OASIS under the path name GON.PAV
/ SPPC.
-
Bonneville Power Administration:
A TTC of 370MW is provided from Sierra's
interconnection with PacifiCorp's Utah division on the Gonder-Pavant
line to Sierra's interconnection with Bonneville Power
Administration at the Hilltop substation. Available transmission
capacity for this path is posted on the OASIS under the path name
GON.PAV / HILLTOP345.
-
Idaho Power Company:
A TTC of 262MW is provided from Sierra's interconnection with
PacifiCorp's Utah division on the Gonder-Pavant transmission
line to Sierra's interconnection with the Idaho Power
Company at the Midpoint substation. Available transmission
capacity for this path is posted on the OASIS under the path
name
GON.PAV / M345.
Pacific Gas & Electric:
A TTC of 105MW is provided from Sierra's
interconnection with PacifiCorp's Utah division on the Gonder-Pavant
line to Sierra's interconnection PG&E at the Donner Summit
Metering Station. Available transmission capacity for this path is
posted on the OASIS under the path name
GON.PAV / SUMMIT120.
Los Angeles Department of Water and Power (LADWP) and the
Intermountain Power Project:
A TTC of 200MW is provided from Sierra's
interconnection with PacifiCorp's Utah division on the Gonder-Pavant
transmission line to Sierra's interconnection with LADWP and other
Intermountain Power Project Parties on the Gonder-IPP transmission
line. Available transmission capacity for this path is
posted on the OASIS under the path name
GON.PAV /
GON.IPP.
Southern California Edison (SCE)"
A TTC of 17MW is provided from Sierra's
interconnection with PacifiCorp's Utah division on the Gonder-Pavant
transmission line to Sierra's interconnection with SCE at the
Control substation. Available transmission capacity for this path is
posted on the OASIS under the path name
GON.PAV / SILVERPEAK55..
top
From Los Angeles Department of Water and Power
(LADWP) and the Intermountain Power Project Parties to:
-
Sierra Pacific Network:
A TTC of 200MW is provided from Sierra's
interconnection with
IPP Parties on the Gonder-IPP line to the Sierra Pacific
Network. Available transmission capacity for this path is
posted on the OASIS under the path name GON.IPP / SPPC.
-
Bonneville Power Administration:
A TTC of 200MW is provided from Sierra's
interconnection with LADWP and the IPP Parties on the Gonder-IPP
line to Sierra's interconnection with Bonneville Power
Administration at the Hilltop substation. Available
transmission capacity for this path is posted on the OASIS
under the path name GON.IPP / HILLTOP345.
-
Idaho Power Company:
A TTC of 200MW is provided from Sierra's
interconnection with LADWP and the IPP Parties on the Gonder-IPP
transmission line to Sierra's interconnection with the
Idaho Power Company at the Midpoint substation. Available
transmission capacity for this path is posted on the OASIS
under the path name
GON.IPP / M345..
Pacific Gas & Electric:
A TTC of 105MW is provided from Sierra's
interconnection with LADWP and the IPP Parties on the Gonder-IPP
line to Sierra's interconnection PG&E at the Donner Summit
Metering Station. Available transmission capacity for this
path is posted on the OASIS under the path name
GON.IPP / SUMMIT120..
PacifiCorp's Utah Division:
A TTC of 200MW is provided from Sierra's
interconnection with LADWP and the IPP Parties on the Gonder-IPP
transmission line to Sierra's interconnection with
PacifiCorp's Utah division on the Gonder-Pavant
transmission line. Available transmission capacity for
this path is posted on the OASIS under the path name
GON.IPP / GON.PAV.
Southern California Edison (SCE):
A TTC of 17MW is provided from Sierra's
interconnection with LADWP and the IPP Parties on the Gonder-IPP
line to Sierra's interconnection with SCE at the Control substation.
Available transmission capacity for this path is posted on
the OASIS under the path
GON.IPP / SILVERPEAK55.
top
From Southern California Edison (SCE) to:
-
Sierra Pacific Network:
A TTC of 17MW is provided from Sierra's
interconnection with
SCE at the Control substation to the Sierra Pacific
Network. Available transmission capacity for this path
is posted on the OASIS under the path name SILVERPEAK55
/ SPPC.
-
Bonneville Power Administration:
A TTC
17MW is provided from Sierra's interconnection with SCE at
the Control substation to Sierra's interconnection with Bonneville
Power Administration at the Hilltop substation. Available
transmission capacity for this path is posted on the OASIS under the
path name SILVERPEAK55 / HILLTOP345.
-
Idaho Power Company:
A TTC
17MW is
provided from Sierra's interconnection with SCE at the
Control substation to Sierra's interconnection with the
Idaho Power Company at Midpoint substation. Available transmission
capacity for this path is posted on the OASIS under the path name
SILVERPEAK55 / M345.
Pacific Gas & Electric:
A TTC
17MW is
provided from Sierra's interconnection with SCE at
the Control substation to Sierra's interconnection PG&E at the
Donner Summit Metering Station. Available transmission capacity for
this path is posted on the OASIS under the path name
SILVERPEAK55 / SUMMIT120.
PacifiCorp's Utah Division:
A TTC
17MW is
be provided from Sierra's interconnection with SCE at
the Control substation to Sierra's interconnection with PacifiCorp's
Utah division on the Gonder-Pavant transmission line. Available
transmission capacity for this path is posted on the OASIS under the
path name
SILVERPEAK55 / GON.PAV.
Los Angeles Department of Water & Power and the Intermountain Power
Project Parties:
A TTC
17MW is
provided from Sierra's interconnection with SCE at
the Control substation to Sierra's interconnection with LADWP and
other Intermountain Power Project Parties on the Gonder-IPP
transmission line. Available transmission capacity for this path is
posted on the OASIS under the path name
SILVERPEAK55 / GON.IPP.