| PRPA Outages |
| Jun 18, 2013 - Dec 15, 2013 |
| Report created on Jun 18, 2013 at 15:00 (MPT) |
| Outage Name |
Outage Id |
Company | Facility | Flow Gate |
Segment/ JOTSFacility |
Original TTC In |
Original TTC Out |
New TTC |
Start Time (MPT) | Stop Time (MPT) | Status | Outage Category |
Outage Type |
Path Impact |
Report TPs |
Annotation | Creation Time (MPT) | EventId |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| TOT-1 LIMIT PER WAPA | 37839 | PRPA | TOT-1A Summer Limit | BOZ-CRG(PRPA) CRG-BOZ(PRPA) |
29.0 29.0 |
29.0 29.0 |
28.0 28.0 |
2013-06-03 10:30 2013-06-03 10:30 |
2013-09-17 00:00 2013-09-17 00:00 |
Active | TRANSMISSION | FORCED | TOT 1A | PRPA | TOT-1A Summer limit | 2013-06-03 10:38 | PRPA20783 | |
| TOT-1 LIMIT PER WAPA | 37782 | PRPA | BOZ-BEA-CRG 345kv | BOZ-CRG(PRPA) CRG-BOZ(PRPA) |
29.0 29.0 |
29.0 29.0 |
0.0 0.0 |
2013-06-26 09:00 2013-06-26 09:00 |
2013-06-27 17:00 2013-06-27 17:00 |
Scheduled | TRANSMISSION | PLANNED | TOT 1A | PRPA | 2013-05-29 10:51 | PRPA20766 |
©2000 webTrans Version 5.0.00 - Open Access Technology International, Inc. All Rights Reserved.