PPW Outages 
Jan 13, 2018 - Jul 16, 2018
Report created on Jan 17, 2018 at 01:00 (PPT)
Outage
Name
Outage
Id
Company Facility Flow
Gate
Segment/
JOTSFacility
Original
TTC In
Original
TTC Out
New
TTC
Start Time (PPT) Stop Time (PPT) Status Outage
Category
Outage
Type
Path
Impact
Report
TPs
Annotation Creation Time (PPT) EventId
  PPW 127298     5760     PPW     Albina-PGE Curtis 115 kV line (Curtis-Delaware section)          PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW) 

  PACW-PACW.PGE(PPW) 
  PACW.PGE-PACW(PPW)   
  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0   
  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0   
  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0 

  415.0 
  415.0   
  2017-12-11 07:30 
  2017-12-11 07:30 

  2017-12-12 07:30 
  2017-12-12 07:30 

  2017-12-13 07:30 
  2017-12-13 07:30 

  2017-12-14 07:30 
  2017-12-14 07:30 

  2017-12-15 07:30 
  2017-12-15 07:30 

  2017-12-18 07:30 
  2017-12-18 07:30 

  2017-12-19 07:30 
  2017-12-19 07:30 

  2017-12-20 07:30 
  2017-12-20 07:30 

  2017-12-21 07:30 
  2017-12-21 07:30 

  2017-12-22 07:30 
  2017-12-22 07:30 

  2018-01-08 07:30 
  2018-01-08 07:30 

  2018-01-09 07:30 
  2018-01-09 07:30 

  2018-01-10 07:30 
  2018-01-10 07:30 

  2018-01-11 07:30 
  2018-01-11 07:30 

  2018-01-12 07:30 
  2018-01-12 07:30 

  2018-01-15 07:30 
  2018-01-15 07:30 

  2018-01-16 07:30 
  2018-01-16 07:30 

  2018-01-17 07:30 
  2018-01-17 07:30 

  2018-01-18 07:30 
  2018-01-18 07:30 

  2018-01-19 07:30 
  2018-01-19 07:30   
  2017-12-11 16:00 
  2017-12-11 16:00 

  2017-12-12 16:00 
  2017-12-12 16:00 

  2017-12-13 16:00 
  2017-12-13 16:00 

  2017-12-14 16:00 
  2017-12-14 16:00 

  2017-12-15 16:00 
  2017-12-15 16:00 

  2017-12-18 16:00 
  2017-12-18 16:00 

  2017-12-19 16:00 
  2017-12-19 16:00 

  2017-12-20 16:00 
  2017-12-20 16:00 

  2017-12-21 16:00 
  2017-12-21 16:00 

  2017-12-22 16:00 
  2017-12-22 16:00 

  2018-01-08 16:00 
  2018-01-08 16:00 

  2018-01-09 16:00 
  2018-01-09 16:00 

  2018-01-10 16:00 
  2018-01-10 16:00 

  2018-01-11 16:00 
  2018-01-11 16:00 

  2018-01-12 16:00 
  2018-01-12 16:00 

  2018-01-15 16:00 
  2018-01-15 16:00 

  2018-01-16 16:00 
  2018-01-16 16:00 

  2018-01-17 16:00 
  2018-01-17 16:00 

  2018-01-18 16:00 
  2018-01-18 16:00 

  2018-01-19 16:00 
  2018-01-19 16:00   
  CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:Prep Work for PGE Delaware Sub Rebuild; PACW to Stay Normal at Albina CB 2P14 for PGE Delaware Rebuild. Note:PACW-PACW.PGE & PACW.PGE-PACW = 299 Winter. Path(Impact):PACW-PACW.PGE(116)PACW.PGE-PACW(116). *115kV,Daily,Return Weekends*     2017-11-15 09:48     127298  
  BRIDGER WEST     5850     PPW               JB345-JBSN(PPW) 
  JBSN-JB345(PPW)   
  950.0 
  1600.0   
  950.0 
  1600.0   
  950.0 
  1600.0   
  2018-01-12 09:00 
  2018-01-12 09:00   
  2018-01-13 10:00 
  2018-01-13 10:00   
  Completed     TRANSMISSION     FORCED      ONPATH     PPW          2018-01-12 08:13     PPW320  
  PPW 126856     5848     PPW     Ponderosa (West): 230/115 kV Bank #1          PONDEROSA115-PONDEROSAPAC(PPW)      270.0      270.0      250.0      2018-01-16 08:00      2018-01-18 15:30      Active     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:PAC to Issue Terminal Clearance on Sw 1D20 to BPA. Note:PONDEROSA115-PONDEROSAPAC =270 Winter.. Path(Impact):PONDEROSA115-PONDEROSAPAC(20). *230kV,Continuous,Include Weekends*     2018-01-09 11:10     126856  
  PPW 128765     5822     PPW     NVE Harry Allen: Phase Shifter #3          REDB-REDBL(PPW) 
  REDBL-REDB(PPW)   
  470.0 
  470.0   
  470.0 
  470.0   
  193.0 
  293.0   
  2018-01-17 07:00 
  2018-01-17 07:00   
  2018-01-19 16:00 
  2018-01-19 16:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Maintenance:Replace Arrestors. Note:REDBL-REDB (TOT 2C N>S) = 193. REDB-REDBL (TOT 2C S>N) = 293. -Net IPP Imports Impact.. Path(Impact):REDB-REDBL(277)REDBL-REDB(177). *345kV,Continuous,Include Weekends*     2017-12-20 08:50     128765  
  PPW 128885     5838     PPW     Crowfoot-Sweet Home section of the Fry-Foster 115 kV line          PACW-NTLOAD(PPW)      9999.0      9999.0      0.0      2018-01-17 07:00      2018-01-18 17:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Maintenance:Distribution Pole Replacement Next to Transmission Line. Note:Sweet Home will be radial from BPA Albany. Network Load Service Arrangements may be required.. Path(Impact):PACW NTLOAD(9999). *115kV,Continuous,Include Weekends*     2018-01-03 10:14     128885  
  PPW 128795     5839     PPW     Jim Bridger-Populus #2 345 kV line          JBSN-JB345(PPW) 
  JBWT-POP(PPW) 
  NUT-PATHC(PPW) 
  POP-JBWT(PPW)   
  1600.0 
  0.0 
  1172.0 
  0.0   
  1600.0 
  0.0 
  1172.0 
  0.0   
  1066.0 
  0.0 
  1055.0 
  0.0   
  2018-01-17 07:00 
  2018-01-17 07:00 
  2018-01-17 07:00 
  2018-01-17 07:00   
  2018-01-17 16:00 
  2018-01-17 16:00 
  2018-01-17 16:00 
  2018-01-17 16:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Maintenance:A condition Str# 4/181; Change SF6 Gauge on 10H340. Note:JBSN-JB345 = 1600. PacifiCorp = 1067. IPCo = 533. Potential Real Time Impact to Jim Bridger Generation.-NUT-PATHC = 1000 Summer/1055 Winter.-JBWT-POP = 1100. POP-JBWT = 1626 (Applies only if both Jim Bridger-Populus #1 & #2 Lines are out of service at the same time).. Path(Impact):NUT-PATHC(117)JBSN-JB345(534)JBWT-POP(0)POP-JBWT(0). *345kV,Continuous,Include Weekends*     2018-01-03 10:15     128795  
  PPW 128119     5840     PPW     Fish Creek Tap-Toketee Switch Station section of the Soda Springs-Toketee Switch Station 115 kV line          HYDROGEN-PACW(PPW)      9999.0      9999.0      0.0      2018-01-17 08:00      2018-01-17 14:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Maintenance:Inspect and Repair Conductor Damaged by Tree at 2x/1. Note:Total Umpqua Hydro Project Generation limited to 112 Summer / 154 Winter MVA-Fish Creek Generation Unavailable for duration of outage-Toketee Plant units 1, 2, 3 off-line for both take out and return to normal switching. Path(Impact):HYDROGEN-PACW (9999). *115kV,Continuous,Include Weekends*     2018-01-03 10:16     128119  
  PPW 128796     5841     PPW     Jim Bridger-Populus #1 345 kV line          JBSN-JB345(PPW) 
  JBWT-POP(PPW) 
  NUT-PATHC(PPW) 
  POP-JBWT(PPW)   
  1600.0 
  0.0 
  1172.0 
  0.0   
  1600.0 
  0.0 
  1172.0 
  0.0   
  1600.0 
  0.0 
  1172.0 
  0.0   
  2018-01-18 07:00 
  2018-01-18 07:00 
  2018-01-18 07:00 
  2018-01-18 07:00   
  2018-01-18 16:00 
  2018-01-18 16:00 
  2018-01-18 16:00 
  2018-01-18 16:00   
  CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     Maintenance:A condition Str 2/161. Note:JBSN-JB345 = 1600. PacifiCorp = 1067. IPCo = 533. Potential Real Time Impact to Jim Bridger Generation.-NUT-PATHC = 1000 Summer/1055 Winter.-JBWT-POP = 1100. POP-JBWT = 1626 (Applies only if both Jim Bridger-Populus #1 & #2 Lines are out of service at the same time).. Path(Impact):NUT-PATHC(117)JBSN-JB345(534)JBWT-POP(0)POP-JBWT(0). *345kV,Continuous,Include Weekends*     2018-01-03 10:16     128796  
  PPW 128764     5821     PPW     NVE Harry Allen: 345/230 kV Bank #3          REDB-REDBL(PPW) 
  REDBL-REDB(PPW) 

  REDB-REDBL(PPW) 
  REDBL-REDB(PPW)   
  470.0 
  470.0 

  470.0 
  470.0   
  470.0 
  470.0 

  470.0 
  470.0   
  470.0 
  470.0 

  470.0 
  470.0   
  2018-01-16 07:00 
  2018-01-16 07:00 

  2018-01-19 07:00 
  2018-01-19 07:00   
  2018-01-16 16:00 
  2018-01-16 16:00 

  2018-01-19 16:00 
  2018-01-19 16:00   
  CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     Maintenance:Replace Arrestors. Note:REDBL-REDB (TOT 2C N>S) = 240. REDB-REDBL (TOT 2C S>N) = 350.. Path(Impact):REDB-REDBL(120)REDBL-REDB(230). *345kV,Continuous,Include Weekends*     2017-12-20 08:48     128764  
  PPW 128989     5843     PPW     Grace: CB L107 including,-Fish Creek-Grace section of the Goshen-Fish Creek-Grace 161 kV line          GSHN-PATHC(PPW) 
  NUT-PATHC(PPW) 
  PATHC-GSHN(PPW)   
  348.0 
  1172.0 
  148.0   
  348.0 
  1172.0 
  148.0   
  200.0 
  859.0 
  0.0   
  2018-01-19 08:00 
  2018-01-19 08:00 
  2018-01-19 08:00   
  2018-01-19 14:00 
  2018-01-19 14:00 
  2018-01-19 14:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Maintenance:Test CTs on L107. Note:NUT-PATHC = 642 Winter. -GSHN-PATHC = 200. PATHC-GSHN = 0. Path(Impact):NUT-PATHC(313)GSHN-PATHC(148)PATHC-GSHN(148). *161kV,Continuous,Include Weekends*     2018-01-04 15:16     128989  
  PPW 128996     5831     PPW     Cascade 115 kV Tie (Path 25 Schedule Limitation)          CRAG-CRAGVIEW(PPW)      45.0      45.0      0.0      2018-01-22 06:00      2018-01-24 17:30      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:Replace Wintu Jct 60kV Switch 37 with a 3 Gap SEECO SCADA operable switch. Note:CRAG-CRAGVIEW = 0. - -. Path(Impact):CRAG-CRAGVIEW(45). *115kV,Continuous,Include Weekends*     2017-12-28 09:53     128996  
  PPW 128998     5832     PPW     Cascade 115 kV Tie (Path 25 Schedule Limitation)          CRAG-CRAGVIEW(PPW)      45.0      45.0      0.0      2018-01-25 05:00      2018-01-25 05:35      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:Exercise Cottonwood CB's 192 & 542. Note:CRAG-CRAGVIEW = 0. - -. Path(Impact):CRAG-CRAGVIEW(45). *115kV,Continuous,Include Weekends*     2017-12-28 09:59     128998  
  PPW 128770     5824     PPW     Cascade 115 kV Tie (Path 25 Schedule Limitation)          CRAG-CRAGVIEW(PPW)      45.0      45.0      45.0      2018-01-27 05:00      2018-01-27 05:05      CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:Cascade 60kV CB 72 Breaker Exercise. Note:CRAG-CRAGVIEW = 0. - -. Path(Impact):CRAG-CRAGVIEW(45). *115kV,Continuous,Include Weekends*     2017-12-20 10:48     128770  
  PPW 128769     5823     PPW     Cascade 115 kV Tie (Path 25 Schedule Limitation)          CRAG-CRAGVIEW(PPW)      45.0      45.0      45.0      2018-01-27 05:30      2018-01-27 05:35      CANCELLED     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:Cascade 115kV CB 112 Breaker Exercise. Note:CRAG-CRAGVIEW = 0. - -. Path(Impact):CRAG-CRAGVIEW(45). *115kV,Continuous,Include Weekends*     2017-12-20 10:44     128769  
  PPW 129758     5854     PPW     Glen Canyon-Sigurd 230 kV line (Open-Ended at Glen Canyon)          GLENCANYON2-PACE(PPW) 
  PACE-GLENCANYON2(PPW)   
  300.0 
  250.0   
  300.0 
  250.0   
  300.0 
  250.0   
  2018-01-29 11:00 
  2018-01-29 11:00   
  2018-01-29 15:00 
  2018-01-29 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:Line Will be Open-Ended at Glen Canyon For Cutover of T1's From Existing Multiplexer to New Mutiplexer. Note:GLC2-PACE & PACE-GLC2 (TOT 2B2) = 0-Net IPP Imports Impact.. Path(Impact):GLENCANYON2-PACE(300)PACE-GLENCANYON2(250). *230kV,Continuous,Include Weekends*     2018-01-16 13:50     129758  
  PPW 129776     5855     PPW     Glen Canyon-Sigurd 230 kV line (Open-Ended at Glen Canyon)          GLENCANYON2-PACE(PPW) 
  PACE-GLENCANYON2(PPW)   
  300.0 
  250.0   
  300.0 
  250.0   
  0.0 
  0.0   
  2018-01-30 07:00 
  2018-01-30 07:00   
  2018-01-30 15:00 
  2018-01-30 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:Line Will be Open-Ended at Glen Canyon For Cutover of T1's From Existing Multiplexer to New Mutiplexer. Note:GLC2-PACE & PACE-GLC2 (TOT 2B2) = 0-Net IPP Imports Impact.. Path(Impact):GLENCANYON2-PACE(300)PACE-GLENCANYON2(250). *230kV,Continuous,Include Weekends*     2018-01-16 14:01     129776  
  PPW 129547     5858     PPW     Kaycee-Midwest section of the Buffalo-Claim Jumper 230 kV line (Midwest: C/S 1H432)          TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOEAST-TOT4B(PPW) 
  WYOEAST-WYOCENTRAL(PPW)   
  638.0 
  170.0 
  638.0 
  950.0   
  638.0 
  170.0 
  638.0 
  950.0   
  600.0 
  145.0 
  600.0 
  945.0   
  2018-01-30 09:00 
  2018-01-30 09:00 
  2018-01-30 09:00 
  2018-01-30 09:00   
  2018-01-30 10:00 
  2018-01-30 10:00 
  2018-01-30 10:00 
  2018-01-30 10:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Relay Maintenance:Replacing Grounded Control Cables. Note:4A/4B Curve 119. WAPAEAST-WAPANORTH (Wheel) = 217. WYOEAST-WYOCENTRAL (4A) = 945. WYOEAST-TOT4B & TOT4B-WYONORTH = 600. 4B Limit = 817.. Path(Impact):WYOEAST-WYOCENTRAL(5)WAPAEAST-WAPANORTH (25)TOT4B-WYONORTH(38)WYOEAST-TOT4B(38). *230kV,Daily,Include Weekends*     2018-01-16 15:04     129547  
  PPW 129778     5856     PPW     Glen Canyon-Sigurd 230 kV line (Open-Ended at Glen Canyon)          GLENCANYON2-PACE(PPW) 
  PACE-GLENCANYON2(PPW)   
  300.0 
  250.0   
  300.0 
  250.0   
  0.0 
  0.0   
  2018-01-31 07:00 
  2018-01-31 07:00   
  2018-01-31 15:00 
  2018-01-31 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:Line Will be Open-Ended at Glen Canyon For Cutover of T1's From Existing Multiplexer to New Mutiplexer. Note:GLC2-PACE & PACE-GLC2 (TOT 2B2) = 0-Net IPP Imports Impact.. Path(Impact):GLENCANYON2-PACE(300)PACE-GLENCANYON2(250). *230kV,Continuous,Include Weekends*     2018-01-16 14:10     129778  
  PPW 129266     5845     PPW     Rock Springs-Point of Rocks-Jim Bridger 230 kV line (Open Ended at Rock Springs)          JBSN-WYOCENTRAL(PPW) 
  THERMALGEN-PACE(PPW) 
  WYOCENTRAL-JBSN(PPW)   
  600.0 
  9999.0 
  600.0   
  600.0 
  9999.0 
  600.0   
  400.0 
  0.0 
  400.0   
  2018-01-31 07:00 
  2018-01-31 07:00 
  2018-01-31 07:00   
  2018-02-01 00:00 
  2018-02-01 00:00 
  2018-02-01 00:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Relay Maintenance:To operate Breakers from Relays. Note:No Impact to 4A/4B or WAPA Wheel with one of two parallel lines out of service between Jim Bridger & Rock Springs. -JBSN-WYOC & WYOC-JBSN = 400. Potential Real Time Impact to Jim Bridger Generation.. Path(Impact):WYOCENTRAL-JBSN(200)JBSN-WYOCENTRAL(200)THERMAL GEN-PACE(9999). *230kV,Daily,Include Weekends*     2018-01-05 13:54     129266  
  PPW 129781     5857     PPW     Glen Canyon-Sigurd 230 kV line (Open-Ended at Glen Canyon)          GLENCANYON2-PACE(PPW) 
  PACE-GLENCANYON2(PPW)   
  300.0 
  250.0   
  300.0 
  250.0   
  0.0 
  0.0   
  2018-02-01 07:00 
  2018-02-01 07:00   
  2018-02-01 15:00 
  2018-02-01 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:Line Will be Open-Ended at Glen Canyon For Cutover of T1's From Existing Multiplexer to New Mutiplexer. Note:GLC2-PACE & PACE-GLC2 (TOT 2B2) = 0-Net IPP Imports Impact.. Path(Impact):GLENCANYON2-PACE(300)PACE-GLENCANYON2(250). *230kV,Continuous,Include Weekends*     2018-01-16 14:16     129781  
  PPW 129269     5846     PPW     Firehole-Monument 230 kV line (open ended at Firehole)          TRONA-NUT(PPW) 
  WAPAEAST-WAPANORTH(PPW) 

  TRONA-NUT(PPW) 
  WAPAEAST-WAPANORTH(PPW)   
  475.0 
  170.0 

  475.0 
  170.0   
  475.0 
  170.0 

  475.0 
  170.0   
  475.0 
  170.0 

  278.0 
  165.0   
  2018-01-31 10:00 
  2018-01-31 10:00 

  2018-02-02 10:00 
  2018-02-02 10:00   
  2018-01-31 14:00 
  2018-01-31 14:00 

  2018-02-02 14:00 
  2018-02-02 14:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Relay Maintenance:WECC MAINTANCE. Note:4A/4B Curve 108. WAPA E/N = 233. WYOE-WYOC = 937.-TRONA-NUT = 278.. Path(Impact):TRONA-NUT(197)WAPAEAST-WAPANORTH (5). *230kV,Continuous,Include Weekends*     2018-01-08 11:07     129269  
  PPW 118182     5280     PPW     Cascade 115 kV Tie (Path 25 Schedule Limitation)          CRAG-CRAGVIEW(PPW) 

  CRAG-CRAGVIEW(PPW)   
  45.0 

  45.0   
  45.0 

  45.0   
  0.0 

  0.0   
  2017-05-31 07:00 

  2018-02-08 07:00   
  2017-05-31 19:00 

  2018-02-08 19:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:Cascade-Benton-Deschutes 60kV Line Section (Wintu Jct-Benton) Cleared. Note:CRAG-CRAGVIEW = 0.. Path(Impact):CRAG-CRAGVIEW(45). *115kV,Continuous,Include Weekends*     2017-04-28 11:23     118182  
  PPW 128461     5810     PPW     Ponderosa (West): 230/115 kV Bank #2 (Trips Checks Including BPA Ponderosa: CB A1815 & CB 1812 and P          PONDEROSA115-PONDEROSAPAC(PPW)      270.0      270.0      250.0      2018-02-15 08:00      2018-02-15 12:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:Trip Checks; PAC to Open Sw's 2D715 & 2D718 to Isolate Xfmr 2 for Trip Checks. Note:PONDEROSA115-PONDEROSAPAC =182 Summer/270 Winter.. Path(Impact):PONDEROSA115-PONDEROSAPAC(20). *230kV,Continuous,Include Weekends*     2017-12-13 14:58     128461  
  PPW 114612     5097     PPW     BPA Malin-Summer Lake 500 kV line          PACW-SMLK(PPW) 
  SMLK-PACW(PPW) 

  PACW-SMLK(PPW) 
  SMLK-PACW(PPW)   
  550.0 
  1187.0 

  550.0 
  1187.0   
  550.0 
  1187.0 

  550.0 
  1187.0   
  550.0 
  1187.0 

  0.0 
  0.0   
  2017-11-28 09:00 
  2017-11-28 09:00 

  2018-02-20 09:00 
  2018-02-20 09:00   
  2017-11-28 15:00 
  2017-11-28 15:00 

  2018-02-20 15:00 
  2018-02-20 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Energization:Sycan 3 Transfer Trip Replacement Trip Checks. Note:PACW-SMLK & SMLK-PACW = 0.-Eliminates ESM Point to Point Service from Troutdale to Summer Lake. Eliminates Ability to Transfer Bridger Generation for Network Load Service to Southern Oregon.. Path(Impact):PACW-SMLK(550)SMLK-PACW(1187). *500kV,Continuous,Include Weekends*     2017-02-07 14:49     114612  
  PPW 128492     5813     PPW     BPA Jones Canyon: Cap Group 1/Section 1 & CB A-1688          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2018-03-19 07:30      2018-03-19 09:30      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:Herbicide Spraying; Leaning Juniper Restricted to 83 MW. Note:Leaning Juniper Restricted to 83 MW. Path(Impact):WIND GEN-PACW(9999). *230kV,Continuous,Include Weekends*     2017-12-14 10:09     128492  
  PPW 117271     5251     PPW     Malin 500 kV Bay including -Captain Jack-Malin #2 500 kV line & BPA Malin-Summer Lake 500 kV line te          PACW-SMLK(PPW) 
  SMLK-PACW(PPW) 

  PACW-SMLK(PPW) 
  SMLK-PACW(PPW) 

  PACW-SMLK(PPW) 
  SMLK-PACW(PPW) 

  PACW-SMLK(PPW) 
  SMLK-PACW(PPW)   
  550.0 
  1187.0 

  550.0 
  1187.0 

  550.0 
  1187.0 

  550.0 
  1187.0   
  550.0 
  1187.0 

  550.0 
  1187.0 

  550.0 
  1187.0 

  550.0 
  1187.0   
  550.0 
  1187.0 

  550.0 
  1187.0 

  550.0 
  1187.0 

  0.0 
  0.0   
  2017-05-01 09:00 
  2017-05-01 09:00 

  2017-09-01 09:00 
  2017-09-01 09:00 

  2017-12-04 09:00 
  2017-12-04 09:00 

  2018-03-19 09:00 
  2018-03-19 09:00   
  2017-05-03 15:00 
  2017-05-03 15:00 

  2017-09-10 15:00 
  2017-09-10 15:00 

  2017-12-11 15:00 
  2017-12-11 15:00 

  2018-03-23 15:00 
  2018-03-23 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Maintenance:BPA DCC to issue a Clearance at Malin: 4580/4592/11L1/11L6 TERMINAL OF CAPTAIN JACK-MALIN 2 500KV LINE; BPA DCC to issue a Clearance at Malin: 4590/4592/11L3/11L7 TERMINAL OF SUMMER LAKE-MALIN NO 1 500KV LINE; South Region to issue a Clearance for Permanent Bus Work Repair at Malin. Note:PACW-SMLK & SMLK-PACW = 0.-Eliminates ESM Point to Point Service from Troutdale to Summer Lake. Eliminates Ability to Transfer Bridger Generation for Network Load Service to Southern Oregon.. Path(Impact):PACW-SMLK(550)SMLK-PACW(1187). *500kV,Continuous,Include Weekends*     2017-04-20 14:24     117271  
  PPW 128490     5814     PPW     BPA Jones Canyon: Cap Group 1/Section 2 & CB A-1689          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2018-03-19 09:30      2018-03-19 11:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:Herbicide Spraying; Leaning Juniper Restricted to 83 MW. Note:Leaning Juniper Restricted to 83 MW. Path(Impact):WIND GEN-PACW(9999). *230kV,Continuous,Include Weekends*     2017-12-14 10:11     128490  
  PPW 129741     5853     PPW     Cove (West): 230/69 kV Bank #2 (T3398)          PACW-ROUNDBUTTE(PPW) 
  ROUNDBUTTE-PACW(PPW)   
  123.0 
  123.0   
  123.0 
  123.0   
  60.0 
  60.0   
  2018-03-19 10:00 
  2018-03-19 10:00   
  2018-03-23 15:00 
  2018-03-23 15:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Maintenance:Differential Relay Maintenance. Note:PACW-RNDBT & RNDBT-PACW = 60.-. Path(Impact):PACW-ROUNDBUTTE(63)ROUNDBUTTE-PACW(63). *230kV,Continuous,Include Weekends*     2018-01-16 10:58     129741  
  PPW 124942     5643     PPW     BPA Jones Canyon-BPA Santiam 230 kV line (Tumble Creek-Jones Canyon section)          WINDGEN-PACW(PPW)      9999.0      9999.0      0.0      2018-05-07 07:00      2018-05-10 15:00      SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:Replace Insulators. Note:Leaning Juniper Generation must be off line before switching the Jones Canyon-Tumble Creek line out of service and again before switching it back in service.-During the line outage, Generation is restricted to 40 mw.. Path(Impact):WIND GEN-PACW(9999). *230kV,Continuous,Include Weekends*     2017-09-21 13:02     124942  
  PPW 128222     5807     PPW     Thermopolis: 230/115 kV Bank #2 (T3735)          TOT4B-WYONORTH(PPW) 
  WAPAEAST-WAPANORTH(PPW) 
  WYOEAST-TOT4B(PPW) 
  WYOEAST-WYOCENTRAL(PPW)   
  638.0 
  170.0 
  638.0 
  950.0   
  638.0 
  170.0 
  638.0 
  950.0   
  543.0 
  145.0 
  543.0 
  945.0   
  2018-05-08 07:00 
  2018-05-08 07:00 
  2018-05-08 07:00 
  2018-05-08 07:00   
  2018-05-25 16:00 
  2018-05-25 16:00 
  2018-05-25 16:00 
  2018-05-25 16:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Maintenance:PACW to Issue a Clearance for Bushing & LTC Maintenance. Note:4A/4B Curve 114. WAPA E/N = 217. WYOE-WYOC (4A) = 945. WYOEAST-TOT4B & TOT4B-WYONORTH = 543. 4B Limit = 760.-Yellowtail South to be determined by WAPA.. Path(Impact):WYOEAST-WYOCENTRAL(5)WAPAEAST-WAPANORTH (25)TOT4B-WYONORTH(95)WYOEAST-TOT4B(95). *230kV,Continuous,Include Weekends*     2017-12-08 09:49     128222  
  PPW 118114     5271     PPW     BPA Jones Canyon: Cap Group 1/Section 2 & CB A-1689          WINDGEN-PACW(PPW) 

  WINDGEN-PACW(PPW) 

  WINDGEN-PACW(PPW)   
  9999.0 

  9999.0 

  9999.0   
  9999.0 

  9999.0 

  9999.0   
  9999.0 

  0.0 

  9999.0   
  2017-08-09 08:00 

  2017-08-16 08:00 

  2018-05-30 08:00   
  2017-08-10 16:00 

  2017-08-17 16:00 

  2018-05-31 16:00   
  SCHEDULED     TRANSMISSION     PLANNED      ONPATH     PPW     Other Utility Request:PCB Diagnostic Service; Leaning Juniper Restricted. Note:Leaning Juniper restricted to 83 MW. Path(Impact):WIND GEN-PACW(9999). *230kV,Continuous,Include Weekends*     2017-04-26 14:29     118114  