Master Transmission Request Schedule - November 1, 2007
Nevada Power Company Transmission Service w/Interconnection Requests - Short Term          
Company Size Point of Receipt Point of Delivery Application Date Commence-ment Term OASIS Posting Initial Scoping Mtg Held SISA Sent SISA
Signed
SIS
Provided
SIS Scoping Meeting FSA Sent FSA
Signed
FS
Provided
Comments
no req rec that a required study
Nevada Power Company Transmission Service w/Interconnection Requests - Long Term          
Company Size Point of Receipt Point of Delivery Application Date Commence-ment Term OASIS Posting Initial Scoping Mtg Held SISA Sent SISA
Signed
SIS
Provided
SIS Scoping Meeting FSA Sent FSA
Signed
FS
Provided
Project
Status
White Pine Energy/GBT 700 MW Harry Allen Mead 230kv 01/09/06 06/01/10 20 years 02/15/06 02/22/06 09/25/06 10/04/06 10/02/06 10/13/06 01/08/07 W/D 3/30/07
White Pine Energy/GBT 500 MW Harry Allen Mead 230kv 01/09/06 06/01/11 20 years 02/15/06 02/22/06 09/25/06 10/04/06 10/02/06 10/13/06 01/08/07 W/D 3/30/07
UAMPS 110 MW Red Butte Mead 230kv 07/25/06 01/01/12 30 years 8/3/06 08/07/06 08/25/06 02/28/07 04/17/06 02/28/07 W/D  5/2/07
UAMPS 50MW Robinson Sub Mead 230kv 09/06/06 01/01/12 30 years 9/14/06 9/20/06 09/14/06 09/29/06 02/09/07 04/17/06 02/09/07 W/D 4/20/07
White Pine Energy 400 MW Harry Allen Mead 230kv 05/23/07 11/01/10 20 years 5/23/07 05/23/07 06/05/07 08/01/07 08/02/07 W/D 9/21/07
White Pine Energy 750 MW Harry Allen Mead 230kv 05/23/07 01/01/12 20 years 5/23/07 05/23/07 06/05/07 08/01/07 08/02/07 W/D 9/21/07
Nevada Power Company NetworkTransmission Service (Affiliate) - Long Term           
Company Size Point of Receipt Point of Delivery Application Date Commence-ment Term   SISA/ISA
Signed
SIS/IS
Provided
SIS Scoping Meeting FSA Sent FSA
Signed
FS
Provided
Project
Status
Nevada Power Co 1000 MW Robinson Sub NPC Uncongested Grid 08/26/05 06/01/10 8/29/05 8/31/05 09/20/05 IRP Filing - Approved-in permitting phase
Nevada Power Co 300 MW Robinson Sub NPC Uncongested Grid 01/06/06 06/01/10 1/11/06 1/11/06 01/24/06 IRP Filing - Approved-in permitting phase
Nevada Power Co 250 MW Robinson Sub NPC Uncongested Grid 01/06/06 06/01/13 1/11/06 1/11/06 01/24/06 IRP Filing - Approved-in permitting phase
Nevada Power Co 100 MW Silver Peak Sub NPC Uncongested Grid 11/17/06 12/01/08 11/22/06 11/22/06 12/11/06 3/23&4/10/07 04/02/07 05/02/07 W/D 6/8/07
Nevada Power Co 340 MW Oreana Sub NPC Uncongested Grid 11/17/06 12/01/08 11/22/06 11/22/06 12/11/06 04/30/07 05/14/07 05/02/07 06/08/07 10/25/07  
Nevada Power Co 7 MW Jean Sub NPC Uncongested Grid 04/18/07 02/01/09 4/26/07 no new study required
Sierra Pacific Power Company Transmission Service w/Interconnection Requests - Short Term          
Company Size Point of Receipt Point of Delivery Application Date Commence-ment Term OASIS Posting Initial Scoping Mtg Held SISA Sent SISA
Signed
SIS
Provided
SIS Scoping Meeting FSA Sent FSA
Signed
FS
Provided
Project
Status
no req rec that a required study
Sierra Pacific Power Company Transmission Service w/Interconnection Requests - Long Term        
Company Size Point of Receipt Point of Delivery Application Date Commence-ment Term   SISA/ISA
Signed
SIS/IS
Provided
SIS Scoping Meeting FSA Sent FSA
Signed
FS
Provided
Project
Status
Presco Energy 8 MW Star Peak Sub Gonder 09/22/06 03/01/07 5 years 11/8/06 10/26/06 11/17/06 No study funds yet 11/08/06 Term req 2/07
PPM 25 MW Midpoint Summit 03/14/07 01/01/08 1 year 3/27/07   W/D req 5/22/07
PPM 25 MW Midpoint Summit 03/14/07 01/01/08 1 year 3/27/07 W/D req 5/22/07
Plumas-Sierra REC 7 MW Gonder Sub Marble Sub 03/29/07 07/01/07 5 years 4/3/07 4/24/07 4/3/07 04/09/07 05/15/07 Not req Study work complete
Silver Peak Geothermal 17 MW Silver Peak SCE 08/20/07 09/01/11 5 years 8/20/07 No study work required
Sierra Pacific Power Company NetworkTransmission Service (Non-Affiliate)  - Long Term          
Company Size Point of Receipt Point of Delivery Application Date Commence-ment Term   SISA/ISA
Signed
SIS/IS
Provided
SIS Scoping Meeting FSA Sent FSA
Signed
FS
Provided
Project
Status
Mt Wheeler Power 42 MW Gonder Sub Machacek Sub 05/26/06 12/01/08 15 years 5/30/06 6/16/06 09/07/06 01/30/07 02/26/07 01/30/07 03/19/07 No longer req Study work complete
Sierra Pacific Power Company NetworkTransmission Service (Affiliate) - Long Term           
Company Size Point of Receipt Point of Delivery Application Date Commence-ment Term   SISA/ISA
Signed
SIS/IS
Provided
SIS Scoping Meeting FSA Sent FSA
Signed
FS
Provided
Project
Status
Sierra Pacific Power 480 MW Tracy SPPCo Uncongested Grid 01/14/04 03/01/06 30 years 07/23/03 08/14/03 IRP Filing - Under construction
Sierra Pacific Power 250 MW Robinson Sub SPPCo Uncongested Grid 08/26/05 06/01/10 8/29/05 8/31/05 09/20/05   IRP Filing - Approved-in permitting phase
Sierra Pacific Power 375 MW Valmy SPPCo Uncongested Grid 02/23/07 01/01/14 3/5/07 4/13/07 3/5/07 03/23/07 10/05/07  
Sierra Pacific Power 150 MW Pav/Gonder 230kV SPPCo Uncongested Grid 04/16/07 01/01/09 4/16/07 Pending IPP int study under LGIP
Sierra Pacific Power 200 MW Mdpt-Humb 345kV SPPCo Uncongested Grid 06/01/07 01/01/11 6/1/07 Pending IPP int study under LGIP