Redispatch Costs


 

Offers of Third Party Redispatch Reliability Redispatch Cost Planning Redispatch Cost Who To Contact Revision History

 

Below are the reported costs to redispatch on the Duke Energy Carolinas transmission system as per CFR §37.6.j.1 and CFR §37.6.j.2.

 

Offers of Third Party Redispatch:

 

CFR §37.6.j.1 "The Transmission Provider must allow the posting on OASIS of any third party offer to relieve a specified congested transmission facility."

Back to Top


 

Reliability Redispatch Cost:

 

CFR §37.6.j.2 "The Transmission Provider must post on OASIS (i) its monthly average cost of planning and reliability redispatch, for which it invoices customers, at each internal transmission facility or interface over which it provides redispatch service and (ii) a high and low redispatch cost for the month for each of these same transmission facilities."

 

Back To Top


 

Planning Redispatch Cost:

 

CFR §37.6.j.2 "The Transmission Provider must post on OASIS (i) its monthly average cost of planning and reliability redispatch, for which it invoices customers, at each internal transmission facility or interface over which it provides redispatch service and (ii) a high and low redispatch cost for the month for each of these same transmission facilities."

 

Back To Top


 

Who To Contact:

 

Questions about redispatch costs can contact the people listed on the Contact Information page under Redispatch Costs.

 

For the entire list of contacts regarding questions about other services such as Transmission Service Requests, tagging, ATC/TTC, Business Practices, Generator Interconnections, etc. please go to the Contacts page on the left pane of OASIS or http://www.oatioasis.com/DUK/DUK_docs/Contacts.

Back To Top


Revision History:

Back To Top